Municipality

Water quality in Adeje

MiCharco brings together official measurements, classifications and recorded incidents for the 9 bathing zones of Adeje, Tenerife. All data comes from official sources, with a direct link to each original source.

Bathing areas
9
With an active situation
0
Last updated
21 Sept 2026

In addition, there are 11 recorded public actions related to sanitation, wastewater treatment and coastal infrastructure in Adeje. See what's being done

Bathing zones in Adeje

View on the map
9 monitored bathing zones

Playa Ajabo

Adeje · South

Excellent99
Latest test
7 Sept 2026 · 15 days ago
Microbiology
E. coli 29 · Ent. 29
Latest official status
Open
Annual quality
Excellent

Playa de la Enramada

Adeje · South

Excellent99
Latest test
7 Sept 2026 · 15 days ago
Microbiology
E. coli 29 · Ent. 29
Latest official status
Open
Annual quality
Excellent

Playa del Bobo

Adeje · South

Good91
Latest test
7 Sept 2026 · 15 days ago
Microbiology
E. coli 9 · Ent. 9
Latest official status
Open
Annual quality
Excellent

Playa del Duque1

Adeje · South

Very good97
Latest test
7 Sept 2026 · 15 days ago
Microbiology
E. coli 110 · Ent. 2
Latest official status
Open
Annual quality
Excellent

Playa Fañabé

Adeje · South

Good94
Latest test
7 Sept 2026 · 15 days ago
Microbiology
E. coli 29 · Ent. 9
Latest official status
Open
Annual quality
Excellent
Moderate82
Latest test
7 Sept 2026 · 15 days ago
Microbiology
E. coli 50 · Ent. 60
Latest official status
Open
Annual quality
Excellent

Playa Torviscas

Adeje · South

Excellent99
Latest test
7 Sept 2026 · 15 days ago
Microbiology
E. coli 60 · Ent. 29
Latest official status
Open
Annual quality
Excellent
Moderate85
Latest test
7 Sept 2026 · 15 days ago
Microbiology
E. coli 30 · Ent. 90
Latest official status
Open
Annual quality
Excellent
Latest test
7 Sept 2026 · 15 days ago
Microbiology
E. coli 29 · Ent. 29
Latest official status
Open
Annual quality
Excellent

See all Tenerife beaches

Recorded incidents in Adeje

See all incidents

Measures & Projects in Adeje

See all actions

200 tonnes of wet wipes removed from the sewer network in southern Tenerife

Entemanser has removed around 200 tonnes of wet wipes and other waste from the 34 wastewater pumping stations it operates in Adeje, Guía de Isora and Granadilla de Abona during 2026. The work has required more than 6,500 hours. A build-up of this waste can reduce pump efficiency, cause blockages and, in serious cases, contribute to sewage overflows or discharges.

Date

10 Sept 2026

Type
In progress
SEWER NETWORKSANITATION
Where

South · Adeje · Guía de Isora · Granadilla de Abona

Who

EntemanserPublic institutions

Solar power installation completed at the Adeje–Arona wastewater treatment plant

A photovoltaic self-consumption installation at the Adeje–Arona wastewater treatment plant was completed in May 2026. The project had an awarded value of approximately €442,980 and reduces the external electricity demand of the wastewater treatment infrastructure.

The installation supports wastewater treatment infrastructure but does not by itself imply a change in bathing water quality.

Investment: Valor de adjudicación: 442.980 euros

Date

May 2026

Type
Completed
TREATMENT
Where

South · Adeje · Arona · Adeje · Arona

Who

Tenerife Island Water CouncilPublic institutions

New five-year operation and investment programme for the Adeje–Arona wastewater system

The Tenerife Island Water Council awarded a five-year contract covering the operation, maintenance and conservation of the Adeje–Arona regional wastewater treatment and reclaimed water system, together with the planned investment and equipment required for the system.

This measure concerns regional wastewater infrastructure and does not by itself indicate current bathing water quality.

Date

27 Mar 2026

Type
Contract awarded
SANITATIONTREATMENT
Where

South · Adeje · Arona · Adeje · Arona

Who

Tenerife Island Water CouncilPublic institutions

CJEU finds further breaches of the EU Urban Waste Water Treatment Directive affecting Tenerife

The Court of Justice of the European Union ruled that Spain had failed to fulfil several obligations under Directive 91/271/EEC in a number of agglomerations covered by case C-433/23, several of them located in Tenerife. The judgment concerns obligations linked to the collection, treatment and monitoring of urban waste water.

A European judgment records past failures and requires them to be corrected. It does not by itself state the situation at any beach on the day it is consulted.

Date

18 Dec 2025

Type
Court judgment
EU COMPLIANCE
Where

Tenerife · Adeje · Arona · Candelaria · Granadilla de Abona · Guía de Isora · Rosario (El) · Santiago del Teide · San Cristóbal de La Laguna · Santa Cruz de Tenerife

Who

European Union – Court of Justice of the European UnionPublic institutions

Adeje–Arona wastewater pumping stations undergo operational testing

The Tenerife Island Water Council carried out operational tests at the main Adeje–Arona wastewater pumping stations and relief infrastructure, including Puerto, Las Vistas, Barranco de Troya and Torviscas.

This infrastructure action does not in itself imply any change in current bathing-water quality.

Date

17 Jul 2025

Type
In progress
INVESTIGATION / MONITORINGSANITATION
Where

South · Adeje · Arona · Adeje and Arona

Who

Tenerife Island Water CouncilPublic institutions

Emergency repair of the Adeje–Arona impulsion pipe

Around 900,000 euros was allocated to the emergency repair of an impulsion pipe in the Adeje–Arona regional system. This infrastructure transports wastewater within the sanitation system, and its correct operation is important for reducing the risk of incidents and discharges.

Date

2025

Type
Announced
EMERGENCY WORKS
Where

Adeje

Who

Cabildo de Tenerife (island council)Public institutions

Urgent measures at the Adeje–Arona treatment plant

The Island Council included around 1.89 million euros for urgent measures at the Adeje–Arona treatment plant. The measure is officially part of the sanitation, treatment and discharge-minimisation programme.

Date

2025

Type
In progress
TREATMENT
Where

Adeje

Who

Cabildo de Tenerife (island council)Public institutions

Relocation of the Playa de Troya wastewater pumping station

The Adeje–Arona sanitation project provides for replacing the existing Metrópolis wastewater pumping station near the Playa de Troya seafront with a new installation farther inland. The project also includes new wastewater transport infrastructure associated with the pumping system. The project budget is approximately €1.91 million.

The project concerns wastewater collection and pumping infrastructure near Playa de Troya. It does not mean that bathing water at the beach is currently contaminated.

Investment: Presupuesto aproximado de 1,91 millones de euros

Date

2024

Type
In progress
SANITATIONSEWER NETWORK
Where

South · Adeje · Adeje · Playa de Troya

Who

Tenerife Island Water CouncilPublic institutions

Improvement of the Adeje–Arona submarine outfall

The Island Council began remodelling and extending the Adeje–Arona submarine outfall, with an investment of over 4 million euros. The works extend the pipeline by about 200 metres and place the discharge point roughly 1,100 metres from the coast at more than 40 metres depth. This infrastructure is associated with the discharge from the Adeje–Arona desalination system; it is not an untreated sewage outfall.

Investment: Inversión superior a 4 millones de euros

Date

2024

Type
In progress
COASTAL WORKS
Where

Adeje

Who

Cabildo de Tenerife (island council)Public institutions

European Commission refers Spain to the CJEU over wastewater failures affecting Tenerife

The European Commission took Spain to the Court of Justice of the European Union over failures to comply with Directive 91/271/EEC on urban waste water treatment. The case covers several agglomerations in Tenerife, among them Adeje-Arona, Añaza, Candelaria, Golf del Sur, Guía de Isora Litoral, La Esperanza-La Laguna Sur-Santa Cruz-Valles, Puerto de Santiago-Playa la Arena, San Isidro-Litoral, Sueño Azul and Valle de la Orotava.

An infringement procedure is brought against Spain and describes unfulfilled obligations at agglomeration level, not the water quality at a beach on a given day. The required works and connections fall to different administrations.

Date

12 Jul 2023

Type
Under investigation
EU COMPLIANCE
Where

Tenerife · Adeje · Arona · Candelaria · Granadilla de Abona · Guía de Isora · Rosario (El) · Santiago del Teide · San Cristóbal de La Laguna · Santa Cruz de Tenerife

Who

European Union – Court of Justice of the European UnionPublic institutions

Western Adeje wastewater infrastructure planned for connection to the Adeje–Arona treatment system

Official infrastructure planning included new pumping and transport works intended to improve the transfer of wastewater from western Adeje towards the regional Adeje–Arona treatment system. The programme includes infrastructure affecting areas such as Sueño Azul, Playa Paraíso and Callao Salvaje. Documented measures include new or upgraded wastewater pumping infrastructure and pressure pipelines designed to improve wastewater transport within the regional sanitation network.

This infrastructure programme concerns wastewater collection and transport. It does not indicate the bathing water quality of any individual beach on the day it is consulted.

Date

2023

Type
Planned
SANITATIONSEWER NETWORK
Where

South · Adeje · West Adeje · Playa Paraíso · Sueño Azul · Callao Salvaje

Who

Tenerife Island Water CouncilPublic institutions