In addition, there are 8 recorded public actions related to sanitation, wastewater treatment and coastal infrastructure in Rosario (El). See what's being done

Bathing zones in Rosario (El)

View on the map
1 monitored bathing zones

Playa de la Nea1

Rosario (El) · East

Good92
Latest test
21 Sept 2026 · 46 days ago
Microbiology
E. coli 9 · Ent. 17
Latest official status
Open
Annual quality
Excellent

See all Tenerife beaches

Recorded incidents in Rosario (El)

See all incidents
Report
Rosario (El)

A video recorded offshore between Radazul and Playa de la Nea showed a continuous turbid discharge from a submarine outfall. The report did not establish a bathing prohibition or confirm that bathing-water quality was affected.

Projects & updates in Rosario (El)

See all actions

New phase of the La Esperanza–Llano del Moro sewer collector

The Cabildo de Tenerife and El Rosario Town Council are carrying out a new phase of the sewer network on calle El Sino, within the La Esperanza–Llano del Moro main collector. The works add more than one kilometre of separate foul and stormwater networks and allow wastewater to be carried towards the main collector and the district treatment system.

This infrastructure action does not in itself imply any change in current bathing-water quality.

Investment: Adjudicación / Awarded amount

Date

3 Jul 2026

Type
Contract awarded
SEWER NETWORK
Where

Calle El Sino · El Rosario · Rosario (El) · Tenerife

Who

El Rosario Town CouncilPublic institutions

Damaged sewer network repaired in Tabaiba Baja

A landslip seriously damaged a section of the municipal sewer network in Tabaiba Baja. The Town Council carried out an emergency repair, reconnected the wastewater pipeline and removed the temporary system used during the incident.

Water checks were carried out after the repair before the bathing restrictions were reviewed.

Date

17 Jan 2026

Type
Completed
EMERGENCY WORKS
Where

Tabaiba Baja · El Rosario · Rosario (El) · Tenerife

Who

El Rosario Town CouncilImplementing body

CJEU finds further breaches of the EU Urban Waste Water Treatment Directive affecting Tenerife

The Court of Justice of the European Union ruled that Spain had failed to fulfil several obligations under Directive 91/271/EEC in a number of agglomerations covered by case C-433/23, several of them located in Tenerife. The judgment concerns obligations linked to the collection, treatment and monitoring of urban waste water.

A European judgment records past failures and requires them to be corrected. It does not by itself state the situation at any beach on the day it is consulted.

Date

18 Dec 2025

Type
Court judgment
EU COMPLIANCE
Where

Adeje · Arona · Candelaria · Granadilla de Abona · Guía de Isora · Rosario (El) · Santiago del Teide · San Cristóbal de La Laguna · Santa Cruz de Tenerife · Tenerife

Who

European Union – Court of Justice of the European UnionPublic institutions

Six major projects to reduce wastewater discharges in Tenerife

The Cabildo is advancing six major hydraulic projects across Tenerife as part of a sanitation and wastewater treatment programme aimed at improving wastewater treatment, reducing discharges into the sea and increasing the reuse of treated water.

Date

2 Jul 2025

Type
In progress
SANITATIONINFRASTRUCTURE
Where

Tenerife · Granadilla de Abona · Guía de Isora · Santa Cruz de Tenerife · San Cristóbal de La Laguna · Rosario (El) · Puerto de la Cruz · Orotava (La) · Realejos (Los) · Arafo · Güímar · Candelaria

Who

Cabildo de Tenerife (island council)Public institutions

ACUAES (Aguas de las Cuencas de España)Public institutions

Tenerife Island Water CouncilPublic institutions

€33.6 million approved for six major hydraulic projects

The Cabildo approved €33.6 million to advance six major hydraulic infrastructure projects across Tenerife, including sanitation measures intended to reduce wastewater discharges.

This infrastructure action does not in itself imply any change in current bathing-water quality.

Date

2 Jul 2025

Type
In progress
SANITATIONINFRASTRUCTURE
Where

Granadilla de Abona · Guía de Isora · Santa Cruz de Tenerife · San Cristóbal de La Laguna · Rosario (El) · Puerto de la Cruz · Orotava (La) · Realejos (Los) · Arafo · Güímar · Candelaria · Tenerife

Who

Cabildo de Tenerife (island council)Public institutions

ACUAES (Aguas de las Cuencas de España)Public institutions

Tenerife Island Water CouncilPublic institutions

New EU court action includes numerous Tenerife wastewater agglomerations

A new action brought by the European Commission before the Court of Justice covers numerous agglomerations in Tenerife for possible failures to meet obligations on the collection and treatment of urban waste water. The agglomerations cited include Buenavista del Norte, El Sauzal, Garachico-La Caleta, Icod de los Vinos, La Matanza, La Victoria, Las Galletas-Las Rosas, Radazul, San Miguel, Tabaiba, Tamaimo and Valle San Lorenzo.

The list of agglomerations cited is not necessarily complete. A pending procedure does not by itself mean a beach is closed or that a specific point is currently polluted.

Date

3 Sept 2024

Type
Under investigation
EU COMPLIANCE
Where

Arona · Buenavista del Norte · El Sauzal · Garachico · Icod de los Vinos · La Matanza de Acentejo · La Victoria de Acentejo · Rosario (El) · San Miguel de Abona · Tenerife

Who

European Union – Court of Justice of the European UnionPublic institutions

European Commission refers Spain to the CJEU over wastewater failures affecting Tenerife

The European Commission took Spain to the Court of Justice of the European Union over failures to comply with Directive 91/271/EEC on urban waste water treatment. The case covers several agglomerations in Tenerife, among them Adeje-Arona, Añaza, Candelaria, Golf del Sur, Guía de Isora Litoral, La Esperanza-La Laguna Sur-Santa Cruz-Valles, Puerto de Santiago-Playa la Arena, San Isidro-Litoral, Sueño Azul and Valle de la Orotava.

An infringement procedure is brought against Spain and describes unfulfilled obligations at agglomeration level, not the water quality at a beach on a given day. The required works and connections fall to different administrations.

Date

12 Jul 2023

Type
Under investigation
EU COMPLIANCE
Where

Adeje · Arona · Candelaria · Granadilla de Abona · Guía de Isora · Rosario (El) · Santiago del Teide · San Cristóbal de La Laguna · Santa Cruz de Tenerife · Tenerife

Who

European Union – Court of Justice of the European UnionPublic institutions

Tabaiba wastewater pumping station relocated and upgraded

The Tabaiba wastewater pumping station was relocated and upgraded to improve wastewater collection and allow additional buildings to connect to the sewer network rather than relying on septic or infiltration systems.

This infrastructure action does not in itself imply any change in current bathing-water quality.

Investment: Aproximado / Approximate

Date

25 Apr 2022

Type
Completed
SANITATIONINFRASTRUCTURE
Where

Tabaiba · El Rosario · Rosario (El) · Tenerife

Who

Cabildo de Tenerife (island council)Public institutions