Playa de las Galletas
Arona · South
MiCharco brings together official measurements, classifications and recorded incidents for the 4 bathing zones of Arona, Tenerife. All data comes from official sources, with a direct link to each original source.
In addition, there are 17 recorded public actions related to sanitation, wastewater treatment and coastal infrastructure in Arona. See what's being done
| Latest official status | ||||||
|---|---|---|---|---|---|---|
Arona · South | Good90 | Open | 19 Oct 2026 18 days ago | E. coli29 Ent.6 | Excellent | 315 mUnauthorised |
Arona · South | Very good95 | Open | 19 Oct 2026 18 days ago | E. coli9 Ent.4 | Excellent | 297 mAuthorised |
Arona · South | Moderate84 | Open | 26 Oct 2026 11 days ago | E. coli9 Ent.24 | Excellent | 303 mAuthorised |
Arona · South | Good94 | Open | 19 Oct 2026 18 days ago | E. coli9 Ent.1 | Excellent | 271 mAuthorised |
Arona · South
Arona · South
Arona · South
Arona · South
| Location | Status | Description | Source | |
|---|---|---|---|---|
| 1 Nov 2026 | Arona | Report Unconfirmed | Diario de Avisos reports images and accounts from Álvaro Rodríguez and Asier Linares showing overflowing drains and a pipe releasing water into the sea at Palm-Mar, Arona. They report odours, wipes and a possible mixture with wastewater after rain. There is no official confirmation of the water’s composition or contamination of a particular beach. November 1 is the publication date; the exact filming date is not established. Unconfirmed report. |
Unconfirmed
Diario de Avisos reports images and accounts from Álvaro Rodríguez and Asier Linares showing overflowing drains and a pipe releasing water into the sea at Palm-Mar, Arona. They report odours, wipes and a possible mixture with wastewater after rain. There is no official confirmation of the water’s composition or contamination of a particular beach. November 1 is the publication date; the exact filming date is not established. Unconfirmed report.
ACUAES has authorised a €2,095,269 tender to complete incoming connections to the Montaña Reverón treatment plant, located in Arona and intended to treat wastewater from eastern Arona and San Miguel de Abona. The works have a five-month execution period. Plant trials are expected in summer 2027, followed by progressive commissioning.
Timeline
27 Oct 2026
ACUAES details the tender and progress of the systems
ACUAES authorises a €2,095,269 tender with a five-month execution period for the final incoming pumping pipelines, part of the terrestrial outfall and the access road. The plant is in its final phase, awaiting completion of its electrical connection following Energy Directorate approval. Arona Este is 73% complete, San Miguel 63% and the Palm-Mar connection 25%, with completion expected in mid-2027. Plant trials are expected in summer 2027, followed by progressive receipt of wastewater. Seven- and four-kilometre terrestrial outfalls have been built to connect to the existing submarine outfalls in both municipalities for surplus not sent to the reuse reservoir. These are infrastructure works, not confirmation of contamination.
27 Oct 2026
Montaña Reverón wastewater treatment plant · Arona · Tenerife
Tenerife Island Water CouncilPublic institutions
ACUAES (Aguas de las Cuencas de España)Implementing body
According to sources at the Cabildo de Tenerife, the contract for renovating the Las Vistas promenade in Arona is expected to be awarded in 2027 and depends on coastal authority approval. The project includes a separate stormwater network and a new wastewater collector along a stretch of almost one kilometre.
8 Oct 2026
Arona · Tenerife
Cabildo de Tenerife (island council)Organiser
Arona Town CouncilPublic institutions
ACUAES reported that approximately €158 million had already been executed within the major Tenerife sanitation and wastewater-treatment programme, representing about 67% of planned execution. The update included commissioning work at the Oeste and Los Letrados systems.
This infrastructure action does not in itself imply any change in current bathing-water quality.
Investment: Ejecutados (≈67% de lo previsto) / Executed (≈67% of planned)
20 May 2026
Guía de Isora · Santiago del Teide · Granadilla de Abona · Arona · San Miguel de Abona · Tenerife
ACUAES (Aguas de las Cuencas de España)Public institutions
Cabildo de Tenerife (island council)Public institutions
Tenerife Island Water CouncilPublic institutions
Los Cristianos beach (Arona) did not receive the Blue Flag for the 2026 season. According to ADEAC, the reason was not achieving an "excellent" water-quality rating in the scientific sampling, one of the required criteria. Arona Town Council stated that the area remained suitable for bathing throughout the period analysed and that in 2025 there were three isolated samplings where the rating moved from "excellent" to "good", never reaching "insufficient". Losing a voluntary award is not a bathing closure and does not affect the historical profile.
7 May 2026
Los Cristianos beach · Arona · Tenerife
Association for Environmental and Consumer Education (ADEAC)Organiser
Arona Town CouncilAuthority addressed
A photovoltaic self-consumption installation at the Adeje–Arona wastewater treatment plant was completed in May 2026. The project had an awarded value of approximately €442,980 and reduces the external electricity demand of the wastewater treatment infrastructure.
The installation supports wastewater treatment infrastructure but does not by itself imply a change in bathing water quality.
Investment: Valor de adjudicación: 442.980 euros
May 2026
Adeje · Arona · Tenerife
Tenerife Island Water CouncilPublic institutions
The Tenerife Island Water Council awarded a five-year contract covering the operation, maintenance and conservation of the Adeje–Arona regional wastewater treatment and reclaimed water system, together with the planned investment and equipment required for the system.
This measure concerns regional wastewater infrastructure and does not by itself indicate current bathing water quality.
27 Mar 2026
Adeje · Arona · Tenerife
Tenerife Island Water CouncilPublic institutions
A press report described the situation along the southern coast of Tenerife (Los Cristianos, Las Vistas, El Camisón and Playa de las Américas) during storm Therese, with debris and wipes in the water and accounts from lifeguards and beachgoers. The article expressly states that the beaches remained open under red flags and were not sealed off. It also notes that the Ministry of Health recorded at least 29 short-duration contamination incidents in the Canary Islands in 2024. No official bathing ban is documented for this episode, so the entry is recorded as context and affects no score.
25 Mar 2026
Los Cristianos · Las Vistas · El Camisón · Playa de las Américas · Arona · Adeje · Tenerife
Residents of La Camella have called for a solution for several homes that, according to them, still depend on septic systems, and report recurring wastewater overflows. The residents are asking to be effectively connected to the sewer network.
The statements recorded here are those of the residents and are not an official finding.
3 Mar 2026
La Camella · Arona · Tenerife
La Camella residentsOrganiser
The Court of Justice of the European Union ruled that Spain had failed to fulfil several obligations under Directive 91/271/EEC in a number of agglomerations covered by case C-433/23, several of them located in Tenerife. The judgment concerns obligations linked to the collection, treatment and monitoring of urban waste water.
A European judgment records past failures and requires them to be corrected. It does not by itself state the situation at any beach on the day it is consulted.
18 Dec 2025
Adeje · Arona · Candelaria · Granadilla de Abona · Guía de Isora · Rosario (El) · Santiago del Teide · San Cristóbal de La Laguna · Santa Cruz de Tenerife · Tenerife
European Union – Court of Justice of the European UnionPublic institutions
ACUAES awarded the works to connect Palm Mar to the regional sanitation system. The project includes a new wastewater pumping station and around 4.5 kilometres of pipeline to the Montaña Reverón treatment system.
This infrastructure action does not in itself imply any change in current bathing-water quality.
Investment: Aproximado / Approximate
27 Nov 2025
Palm Mar · Arona · Tenerife
ACUAES (Aguas de las Cuencas de España)Public institutions
ACUAES authorised the tender documents for a new pumping station and a pipeline of about 4.5 kilometres. The works connect Palm-Mar to the sanitation system instead of keeping its current discharge.
Investment: 4.485.956 euros de obra más 298.853 euros de dirección
24 Jul 2025
Arona · Tenerife
ACUAES (Aguas de las Cuencas de España)Public institutions
The Tenerife Island Water Council carried out operational tests at the main Adeje–Arona wastewater pumping stations and relief infrastructure, including Puerto, Las Vistas, Barranco de Troya and Torviscas.
This infrastructure action does not in itself imply any change in current bathing-water quality.
17 Jul 2025
Adeje and Arona · Adeje · Arona · Tenerife
Tenerife Island Water CouncilPublic institutions
ATAN and Alianza Local organised a demonstration calling for transparency and action on polluting discharges along Tenerife’s southern tourist coast.
The event focused on Playa Honda and the Las Américas area. This record documents civil-society action; it is not a bathing-water incident.
25 May 2025
Playa Honda · Las Américas · Arona · Tenerife
Tenerife Friends of Nature Association (ATAN)Organiser
Alianza LocalOrganiser
A new action brought by the European Commission before the Court of Justice covers numerous agglomerations in Tenerife for possible failures to meet obligations on the collection and treatment of urban waste water. The agglomerations cited include Buenavista del Norte, El Sauzal, Garachico-La Caleta, Icod de los Vinos, La Matanza, La Victoria, Las Galletas-Las Rosas, Radazul, San Miguel, Tabaiba, Tamaimo and Valle San Lorenzo.
The list of agglomerations cited is not necessarily complete. A pending procedure does not by itself mean a beach is closed or that a specific point is currently polluted.
3 Sept 2024
Arona · Buenavista del Norte · El Sauzal · Garachico · Icod de los Vinos · La Matanza de Acentejo · La Victoria de Acentejo · Rosario (El) · San Miguel de Abona · Tenerife
European Union – Court of Justice of the European UnionPublic institutions
Works continued on the Arona Este–San Miguel sanitation system, including wastewater pumping and collector infrastructure around Tamaide, Las Chafiras, Las Galletas and Guaza linked to the Montaña Reverón treatment system.
This infrastructure action does not in itself imply any change in current bathing-water quality.
8 May 2024
San Miguel de Abona and Arona · San Miguel de Abona · Arona · Tenerife
ACUAES (Aguas de las Cuencas de España)Public institutions
The European Commission took Spain to the Court of Justice of the European Union over failures to comply with Directive 91/271/EEC on urban waste water treatment. The case covers several agglomerations in Tenerife, among them Adeje-Arona, Añaza, Candelaria, Golf del Sur, Guía de Isora Litoral, La Esperanza-La Laguna Sur-Santa Cruz-Valles, Puerto de Santiago-Playa la Arena, San Isidro-Litoral, Sueño Azul and Valle de la Orotava.
An infringement procedure is brought against Spain and describes unfulfilled obligations at agglomeration level, not the water quality at a beach on a given day. The required works and connections fall to different administrations.
12 Jul 2023
Adeje · Arona · Candelaria · Granadilla de Abona · Guía de Isora · Rosario (El) · Santiago del Teide · San Cristóbal de La Laguna · Santa Cruz de Tenerife · Tenerife
European Union – Court of Justice of the European UnionPublic institutions
New district treatment plant designed for 240,000 population equivalent, declared of general state interest. The official project record states an estimated investment of €107 million and an execution status.
Investment: Inversión estimada de 107 millones de euros
23 Jun 2020
Arona · San Miguel de Abona · Tenerife
Ministry for the Ecological Transition and Demographic ChallengePublic institutions